Show/Hide

Important Updates:

Marquette County has a new Welcome Center!  More...

 

HIGHWAY DEPARTMENT NOTIFICATIONS

Print
Press Enter to show all options, press Tab go to next option

News Release

 

Weekly Construction Update No. 4

 

Project ID: 6711-00-70

Highway: IH 39 – CTH K (Lake Street to Freedom Road)

Location: CTH D, Marquette County

Schedule: August 28, 2017 to May 15, 2018; Interim completion date of November 16, 2017

Description: The work under this contract shall consist of excavation common, pit run, shot rock, base aggregate dense, salvaged asphaltic pavement shoulder, HMA pavement, riprap, guardrail, permanent signing, pavement marking, erosion control, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

Traffic Impacts: CTH D will remain closed between Lake Street and Freedom Road. Traffic is detoured via CTH M, STH 23, STH 22, and CTH F.

Work Completed since last update: September 11, 2017 to September 17, 2017

1. Arbor Green finished installation of silt fence at east end of the project limits.

2. Integrity Grading and Excavating continued excavation, shot rock, and pit run work, and began placing riprap.

Anticipated work schedule for this week: September 18, 2017 to September 24, 2017

1. Integrity Grading and Excavating will finish excavation, shot rock, and pit run work, and will continue placing riprap.

Anticipated work schedule for next week: September 25, 2017 to October 1, 2017

1. Integrity Grading and Excavating will finish any excavation, shot rock and pit run work, and riprap operations. Will begin to place 1 ¼-inch and recycled asphaltic material on fishing platforms.

Please note that all work is weather dependent.

THE CAUSEWAY WILL BE CLOSED STARTING MONDAY AUGUST 28TH

LET    (award bid to contractor)                 = July 11th, 2017

 

Construction  (starting)                              =  August 28th. 2017  causeway will be closed.

                                                                         

Once the closure of the County “D” is started it will remain closed for a duration of approx.….60 working days.  There will be a detour route in place for this project.

The detour route will consist of CTH “D”, CTH “F”, STH 22, STH 23, and CTH “M”.

Construction   (ending for winter season)          = November 16th, 2017

Plans are to have all excavation completed, rock placed, signing installed erosion control done, base material placed, binder asphalt mat installed, with late season pavement makings

Construction  (resume in spring)                         = April 16th, 2018

Finish the project, using approx... 5 working days of one lane closures to complete the finished asphalt surface mat, any settled recycled asphalt shoulders, and pavement markings.